the story of Belle strata (not yet complete!)
The original bungalow while still attached to the 2-storey at the other end of the property.
Cribbing was placed in the basement under the floor of the bungalow in order to raise it off of the foundation.
Once lifted off of the foundation, the bungalow was slowly moved onto two used school bus frames.
The bungalow has been moved enough to partially rest on the school bus frames.
The bungalow is completely off of the foundation and resting on the bus frames waiting to be ferried across the property.
Ferrying of the bungalow begins across the property.
The bungalow has made it to the other end!!
The bungalow was turned and then carefully placed on a newly constructed concrete basement.
An earlier picture of the start of the formwork construction needed to build the basement.
Basement formwork completed showing doors and windows
The bungalow being moved onto the completed concrete basement.
The clapboard siding was removed and sold to someone for reuse. The bungalow, now seated firmly on the basement, is in the midst of being covered by formwork to achieve the concrete strata evident in the basement walls below.
The foam layer underneath the concrete strata provide an R-value of 40 in the walls of the bungalow.